Oil & Gas in the UK

The UK oil and gas industry is in its sixth decade of offshore production. The sector is directly responsible for over 30,000 jobs. OEUK estimated that in 2022 a total of almost 120,000 jobs were supported directly or indirectly by the UK upstream oil and gas industry with a further 60,000 jobs supported in the wider economy.

Background and recent developments

The UK’s oil and gas sector is dominated by production from offshore areas, which account for virtually all of UK output [1].

Production of natural gas began in 1967 with the West Sole field in the Southern North Sea. Offshore oil production began with the Argyll field in the Central North Sea (CNS) in 1975. At the start of the industry in the 1960s and 1970s production was dominated by a small number of very large fields, such as Indefatigable (Inde), Leman, Forties, Brent, Ninian and Piper. That era also saw the development of a number of key offshore pipelines.

UK oil and gas production now comes from almost 300 fields, many of them small and others that are technically complex to produce from, both of which tend to increase unit development and production costs. By the end of 2022, some 47 billion barrels of oil equivalent (boe) had been recovered from the UK and UK Continental Shelf (UKCS).

Having a steady stream of new field start-ups is crucial to ensuring the basin's remaining potential is achieved, although the sector recognises concerns expressed by many about climate change and the need to balance meeting domestic energy supplies and supporting jobs in the energy sector with decarbonisation and ensuring an economic return for future extraction. 

 

Key Economic parameters

Oil and Gas prices

The charts below show the volatile nature of both oil and gas prices. Oil prices are determined on global markets and the same is increasingly true of gas prices.

Figure 1. Monthly and Annual Average Brent Crude Oil Spot Prices ($/barrel)

Source: Monthly average dollar Brent oil price, World Bank Commodity Price Data (The Pink Sheet) 

The data presented in Figure 1 above are available on request from the UK EITI Secretariat.

Figure 2. Monthly and Annual Average Brent Crude Oil Spot Prices (£/barrel)

Sources: Monthly average dollar Brent oil price, World Bank Commodity Price Data (The Pink Sheet)
Monthly average £/$ exchange rate Bank of England series XUMAUSS 

The data presented in Figure 2 above are available on request from the UK EITI Secretariat.

Figure 3. Monthly and Annual Average NBP Natural Gas Spot Prices

 

Source: Ofgem.

The data presented in Figure 3 above are available on request from the UK EITI Secretariat.

Additional information: A therm is a unit used to measure gas production; gas prices are still frequently reported in terms of pence per therm (p/therm). One therm is approximately equal to 29.307 kWh.

Production and Trade

Production on the UKCS is currently split roughly 60:40 between oil production and natural gas production (Figure 4).

Figure 4. UK Oil and Net Gas Production [2].

 

Source: NSTA based on DESNZ data 

The data presented in Figure 4 above are available on request from the UK EITI Secretariat.

Net natural gas production equals gross production less producers' own use, that is the gas used in the course of production of oil and gas and therefore not available for sale to end users. The NSTA publishes data relating to production of UK oil and gas, including production data for individual fields, production and expenditure projections and data on UK upstream oil and gas income and expenditure.

Combined oil and gas production volumes from the UKCS peaked in 1999 at 4.5million boe/day and declined to 1.4 million boe/day by 2014 – a consequence of natural reservoir decline in existing fields combined with fewer/smaller developments. Between 2014 and 2019, however, this trend was reversed and production on the UKCS increased to 1.7 million boe/day before falling to 1.4 million boe/day in 2023.

Table 1. Data on the volume and value of UK oil production and trade

NYA=not yet available

Sources: Energy Trends Table 3.10 (DESNZ, March 2024), DUKES 2023 Table 1.2 (DESNZ, July 2023) and (for production values) NSTA estimates

Table 2. Data on the volume and value of UK natural gas production and trade

NYA=not yet available

Sources: Energy Trends Table 4.2 (DESNZ, March 2024), DUKES 2023 Table 1.2 (DESNZ, July 2023) and (for production values) NSTA estimates

The data presented in Tables 1 and 2 above are available on request from the UK EITI Secretariat.

In 2022 domestic production of oil was equivalent to around 61% of UK oil consumption including non-energy demand and marine bunkers (down from 72% in 2021); gross domestic production of natural gas was equivalent to 54% of UK natural gas consumption (up from 42% in 2021). 

The two charts below show, respectively, the destinations of UK oil production and the sources of UK oil supply. Most UK oil production is exported and most UK refinery supply comes from imports.

 

Figure 5. Destination for total UK primary oil production, 2016–2022

 

Sources: DUKES 2023 (DESNZ July 2023)

The data presented in Figure 5 above are available on request from the UK EITI Secretariat.

Figure 6. Ways UK refinery demand was met by imports and UK production, 2018-2022

 

Sources: As figure 5.

The data presented in Figure 6 above are available on request from the UK EITI Secretariat.

The UK benefits from diverse and flexible sources of gas supply. The UK has one of the largest and most liquid gas markets in Europe, with extensive import infrastructure and a diverse range of gas supply sources: pipelines from Norway, Belgium and the Netherlands, domestic production, and the Liquefied Natural Gas (LNG) terminals to bring in gas from around the world. Figure 7 below shows the sources of UK gas supply in recent years. These can change quickly and significantly.

 

Figure 7. Sources of Annual UK Gas Supply - year to date

 

Sources: Energy Trends (DESNZ, March 2024)

The data presented in Figure 7 above are available on request from the UK EITI Secretariat.

As illustrated in Figure 8, below, production of oil from existing fields typically declines over time as reservoir pressure falls. For overall production to increase generally requires several large fields (or major incremental projects in existing fields) to come onstream. Failing that, overall production will continue to decline.

Figure 8. UK oil production by year of field start-up

 

Source: Petroleum Production Reporting System, (NSTA, April 2024)

The data presented in Figure 8 above are available on request from the UK EITI Secretariat.

The UK is still a significant oil and gas producer, being responsible for 0.8% of global production of oil and 0.9% of global production of natural gas in 2022, when the UK was the 23rd largest producer of oil and gas (20th largest of oil and 21st largest of gas) [3].

Cost Environment

As shown in Figure 9, total UK upstream expenditure peaked in 2014 at £35.4 billion in 2023 prices and fell to £13.1 billion in 2020 before rising to £15.4 billion in 2022 and 2023. 

Figure 9. UK upstream oil and gas expenditure

 

Source: UK upstream income and expenditure

The data presented in Figure 9 above are available on request from the UK EITI Secretariat.

Government Revenues

In addition to taxation, the extractive sector in the UK pays relatively small amounts to government by way of licence fees and other levies. These payments are summarised later in this report.

The level of government revenues from taxes on production of oil and gas is dependent on rates of taxation and adjusted profitability which is driven by a combination of production volumes, commodity prices and cost levels. Historical data by financial year since 1976/77 on upstream oil and gas taxes, including petroleum licence fees, are shown in constant price terms in Figure 10.

Figure 10. Government Revenues from UK Oil and Gas Production

 

Source: NSTA, Government revenues from UK oil and gas production (March 2024)

The data presented in Figure 11 above are available on request from the UK EITI Secretariat.

The overall totals reflect both the combination of Ring Fence Corporation Tax (RFCT)/Supplementary Charge (SC) and Petroleum Revenue Tax (PRT) and of net payments and receipts by individual companies. The overall net repayments reflect the low level of oil (and gas) prices and companies’ varying exposure across their portfolios to the four main phases of upstream activity (exploration, development, production and decommissioning).

A few companies paid significant amounts, many paid nothing and some received significant repayments of tax paid in previous years. In future years, with the permanent zero-rating of PRT from the start of 2016, net PRT receipts will be negative, with the carry-back of largely decommissioning-related losses resulting in significant repayments of PRT paid in previous years. 

UK Government accounts are compiled on a financial year basis and the figures reported are consistent with annual totals reported in them on a cash basis.

Table 3 includes estimates of the amounts of RFCT plus SC paid annually in respect of UK upstream oil and gas production activities, i.e. the exploration and productions stage (described for simplicity as “offshore” CT), of Energy Profits Levy (EPL) and of PRT.

In addition to the cash receipts series published by HMRC that is tabulated below, tax receipts are also reported by the ONS on an accruals basis. The accruals basis shows when the tax liability arises, i.e. it matches the taxes arising to taxable income as it is earned. There is usually a timing difference between when the tax liability arises and when it is paid. Tax is usually paid after the liability arises so the tax cash payments in one time period may not match the tax liability for the same period.

For example, a tax liability of £120 million may arise in one tax year (£120 million recorded on an accruals basis); this may be paid in three equal instalments, two in the same tax year (£80 million recorded that year on a cash basis) with one final instalment the next tax year (£40 million recorded in the next tax year on a cash basis). Over a longer timeframe, the same amounts are captured by these two different mechanisms of recording payments, but in the short term there will be a mismatch in amounts. This results in different series being published for corporation tax receipts/repayments. Table 3 below therefore also includes receipts on an accruals basis.

Table 3. UK Government Revenues from Upstream Oil and Gas
HMRC Receipts by Financial Year (Cash) (£million)
Financial YearRing Fence Corporation Tax and Supplementary ChargeEnergy Profits LevyPetroleum Revenue TaxTotal Upstream Oil and GasTotal HMRC ReceiptsUpstream Oil and Gas Share of Total (%)
2018-191,9120-7441,168621,0540.2%
2019-201,2740-408866633,3160.1%
2020-214980-241257583,9670.0%
2021-221,9960-5521,444715,6820.2%
2022-236,6132,632-2349,011788,5821.1%
HMRC Receipts by Calendar Year (Cash) (£million)
Calendar YearRing Fence Corporation Tax and Supplementary ChargeEnergy Profits LevyPetroleum Revenue TaxTotal Upstream Oil and GasTotal HMRC ReceiptsUpstream Oil and Gas Share of Total (%)
20181,9690-8171,152612,8650.2%
20191,4840-3191,165635,0780.2%
20206610-431230569,6030.0%
20211,3340-360974696,1200.1%
20225,4691,660-3916,738765,1250.9%

2023

3,727

3,702

-332

7,097

821,113

0.9%

Source: HMRC tax receipts and National Insurance contributions for the UK

UK Government Receipts by Financial Year (Accruals) (£million)

Financial YearRing Fence Corporation Tax and Supplementary ChargeEnergy Profits LevyPetroleum Revenue TaxTotal Upstream Oil and GasTotal Public Sector Taxes and Social ContributionsUpstream Oil and Gas Share of Total (%)
2018-191,8670-7441,123730,1420.2%
2019-209840-409575738,6040.1%
2020-216910-241450706,3840.1%
2021-223,1420-5522,590829,9680.3%
2022-2310,0934,259-23414,118924,4661.5%
UK Government Receipts by Calendar Year (Accruals) (£million)
Calendar YearRing Fence Corporation Tax and Supplementary ChargeEnergy Profits LevyPetroleum Revenue TaxTotal Upstream Oil and GasTotal Public Sector Taxes and Social ContributionsUpstream Oil and Gas Share of Total (%)
20181,9120-8171,095717,2640.2%
20191,2720-319953738,5550.1%
20204960-43165700,3370.0%
20211,9600-3601,600797,3150.2%
202210,0033,395-39113,007902,4931.4%

2023

5,616

2,884

-332

8,168

964,733

0.8%

Source: Public sector current receipts: Appendix D (accruals).

The data presented in Table 3 above are available on request from the UK EITI Secretariat.

Differences between reconciled EITI amounts and HMRC statistics

There can be differences between the cash totals reported above for RFCT/SC/EPL and PRT, based on published HMRC statistics, and the post-reconciliation totals reported in annual reconciliation reports. These totals and the differences are given in the table showing “Differences between reconciled upstream oil and gas tax payments in EITI Reports and cash payments currently reported in HMRC statistics” on the NSTA website.

The main reason for the difference between the total of RFCT/SC reconciled for EITI and the total published in HMRC statistics are that HMRC statistics are, at least for recent years, provisional (prior to disaggregation and allocation between payments inside and outside the ring fence). 

When oil and gas companies make corporation tax payments they are not obliged to inform HMRC whether such payments relate to RFCT/SC/EPL or mainstream CT. Since 2014, to assist HMRC in relation to EITI reporting, many companies do report the split of payments as they are made to HMRC. Once the tax payment deadline has passed and all tax instalments have been received, HMRC’s statistics team undertakes work to disaggregate these payments made for a group of companies and to re-allocate them into ring fence and non-ring fence payments. HMRC statistics are thus provisional and subject to change, often up to 18 months after the tax year has ended.

For PRT, the discrepancy is primarily the result of timing differences between payments and repayments being made and the date that they are recorded on HMRC’s systems.

Because corporation tax is levied on company level profits and companies can be engaged in both extractive and non-extractive activities, it is not possible to identify how much CT is paid by other extractive industries (i.e. those engaged in mining and quarrying). Estimates of the CT paid by the mining and quarrying sector are published annually by HM Revenue & Customs (HMRC) and include oil and gas and mining support service activities. They are on a liability basis for financial years rather than a cash basis for calendar years.

Visit the NSTA website

Reserves and forecasts

Full details of the assumptions underpinning forthcoming years in the Budget cycle relating to projected production, commodity prices and revenue forecasts are provided by the independent Office for Budget Responsibility.

Figure 11 below shows that early discoveries tended to be much larger than more recent exploration successes have been with very little being added to the known resource base in recent years. The rate of production has varied over time but is now significant in comparison with the discovered resource base. As shown in figures 12 and 13 below, it is expected that production rates for oil and, especially, gas will decline from now on so extraction will not continue for a few years and then just stop. Despite the expected falls in demand for oil and gas, the UK is expected to remain a net importer of both until at least 2050.

Figure 11. Recoverable UK oil and gas reserves discovered and produced

Source: NSTA analysis of Lens data from Wood Mackenzie, April 2024

Figure 12. Projections of UK Oil Demand and Production

 

Source: Climate Change Committee's Balanced Net Zero Pathway (CCC BNZP) and Department for Business, Energy and Industrial Strategy (now DESNZ) Net Zero Strategy (DESNZ NZS) demand projection and latest NSTA production projection, all as published in March 2024 at https://www.nstauthority.co.uk/data-and-insights/insights-and-analysis/production-and-expenditure-projections/

 

Figure 13. Projections of Gross UK Gas Demand and Production

Source: As Figure 12.

 

Employment

In addition to direct employment in oil and gas companies there is a significant number of jobs in companies providing support activities. Official estimates for both are tabulated below:

Table 4. Direct employment (Great Britain not United Kingdom) 
Thousands20182019202020212022
Extraction of crude petroleum and natural gas12,80013,30014,40011,70011,400
Support activities for petroleum and natural gas extraction18,10017,10015,50014,90016,200
Oil and gas extraction and support services30,90030,40029,90026,60027,600

Source: Business Register and Employment Survey (Table 2a) 

The data presented in Table 4 above are available on request from the UK EITI Secretariat.

Additional information on employment in the UK oil and gas industry, including the UK supply chain, is published by OEUK. This information includes estimates of the indirect and induced jobs that depend on the UK’s upstream oil and gas sector. In addition, OEUK provide regional breakdowns of their estimates. Note that the direct employment estimates reported by OEUK differ from the ONS estimates, especially after 2019.

 

Table 5. Total employment supported by the UK Upstream Oil and Gas Industry 
 
Type20182019202020212022
Direct30,40030,30025,80028,40030,000
Indirect116,100121,90091,70093,900100,000
Induced113,400108,70061,00078,50090,000
Total employment259,900260,900178,500200,800220,000
Direct plus indirect146,500152,200117,500122,300130,000
Indirect % of direct plus indirect      79%80%78%77%77%

Where:

  • Direct jobs - are those specifically within the oil and gas sector i.e. employed by companies operating in the extraction of oil and gas and associated services.
  • Indirect jobs - are those in the broader supply chain providing the goods and services i.e. employment as a result of supply chain effects caused by oil and gas sector activity.
  • Induced jobs - are those in the wider economy supported by the oil and gas sector i.e. employment supported by the expenditure of income from the oil and gas sector.

Source: p.17 in Workforce Insight 2023 OEUK, December 2023 (for 2022), Figure 1 in Workforce Insight 2022, OEUK, December 2022 and Figure 1 in Workforce & Employment Insight 2021, OGUK (now OEUK), August 2021 (for 2018).

Shale gas

Research by the BGS indicates that there are potentially large volumes of shale gas beneath the UK.

Further exploration would be required before the full extent of these resources is known and the amount of gas that is technically and commercially recoverable can be estimated.

UK licence and fiscal terms do not generally differentiate between conventional and unconventional hydrocarbon activities. For example, the Onshore Allowance (an allowance against the SC which ensures that otherwise economic developments are not uncommercial) is applicable to both new conventional oil and gas as well as to shale gas developments. As PEDLs do not grant automatic rights to operations such as drilling or hydraulic fracturing, any company looking to develop shale will also need to obtain all necessary permissions, like planning and environmental permits.

To date, a range of measures specific to hydraulic fracturing and the shale industry have been put in place to ensure that exploration is safe and environmentally sound. The Infrastructure Act 2015 specifies thirteen conditions that need to be met before a hydraulic fracturing consent will be issued, including public notification and a scheme to provide financial or other benefit for the local area. The government has also put in place regulations which ensure that high-volume hydraulic fracturing cannot take place within 1,200 metres beneath the surface of National Parks, the Broads, Areas of Outstanding Natural Beauty, World Heritage Sites and areas that are most vulnerable to groundwater pollution.

Following its analysis of hydraulic fracturing operations in 2018, the Oil and Gas Authority (now the North Sea Transition Authority) has found that it is not currently possible to accurately predict the probability or magnitude of earthquakes linked to fracking operations. On this basis, and following the significant disturbance that has been caused to local people following seismic events in August 2019, caused by further operations at Preston New Road, Lancashire, on 2 November 2019 the BEIS Secretary of State announced a moratorium on fracking with immediate effect.

On 4 November 2019, Ministers issued a Written Ministerial Statement that sets out the Government’s position – namely that Government will no longer be supporting further hydraulic fracturing activities in England at this time. The statement sets out that there will be a presumption against Ministers issuing further Hydraulic Fracturing Consents, which would only be altered if compelling new evidence comes to light.

Petroleum licensing functions are devolved to the Welsh Ministers. The Welsh Government petroleum policy, published via a written statement on 10th October 2018, is to not undertake any new petroleum licensing in Wales, or support applications for hydraulic fracturing petroleum licence consents.

 

Written Ministerial Statement

Legal framework and licensing

The Petroleum Act 1998 vests rights to oil and gas (petroleum) resources in England and on the UK Continental Shelf (UKCS) in the Crown.

The Act gives the NSTA powers to grant licences that confer exclusive rights to “search and bore for and get” petroleum. Each of these licences confers such rights over a limited area and for a limited period. There are separate licensing regimes for offshore (seaward) and onshore (landward) areas, with distinct licences in each [4].

Licences are generally awarded in periodic “rounds” subject to a requirement that the holder will make annual payments (known as “licence rental fees”). These payments are calculated on the basis of the area under licence and incorporate an escalating scale of pre-determined rates per square kilometre. This is to encourage licensee companies to relinquish acreage not undergoing productive activity, thus making it available for relicensing to other potential interested applicants. The vast majority of licence rental fees come from offshore licensing. Receipts of petroleum licences under the Petroleum Act 1998 are collected by the NSTA for payment to the Consolidated Fund.

Licensing in Scotland and Wales  is now devolved. The Petroleum (Production) Act (Northern Ireland) 1964 vests the property in oil and gas in Northern Ireland, with certain exceptions, in the Department for the Economy (DfE). Northern Ireland’s offshore waters are subject to the same licensing regime as the rest of the continental shelf.

The NSTA publishes current oil and gas licences and licence reports under their Petroleum e-business assignments and relinquishment system (PEARS). The NSTA also publishes offshore and onshore maps which are available for nil cost; these interactive maps allow users to find the co-ordinates of each licence and download at nil cost, individual licences. The NSTA Regulatory framework sets out how they regulate the exploration and development of the UK's offshore and onshore oil and gas resources. The Northern Ireland DfE issues separate onshore licences independently of the NSTA and publishes current licences and a map showing licence areas.

Award and transfer of licences in Great Britain and on the UKCS

The NSTA works to maximise economic recovery of the nation’s petroleum resources. The government has essential pre-requisites for licence applicants, such as requiring the would-be licensee to have a fixed place of business within the UK.

Licences are awarded during regular competitive onshore and offshore licensing rounds once the NSTA has been satisfied that the licensee has met the necessary technical and financial requirements [5]. This method of licensing aims to optimise recovery of the UK’s remaining petroleum resources. Out-of-round licence applications are possible but only in exceptional circumstances.  Further Information on licensing activity is available on the NSTA website. Licensing rounds are announced in the Official Journal of the European Union and assessed against a publicly announced set of criteria[6]. 

Each licence takes the form of a deed, which binds the licensee (either a single company or several working together and bound under joint and several liability) to obey the licence conditions regardless of whether or not they are using the licence at any given moment. The NSTA (and DECC previously) regulates the transfer of licence interests in order to enforce its policy objectives. A company that is party to a licence may wish to sell its interest or a part of it, to another company. It requires the NSTA’s permission to do so [7]. 

Licence applications and interests attract fees and charges payable by the applicant or licensee. Each licence carries an annual charge, commonly called a rental. Rentals serve the double purpose of incentivising licensees to work their whole licensed areas and to surrender acreage they do not intend to exploit. Rentals are due every year on the licence anniversary and are charged at a variable rate on each square kilometre that the licence covers at that date. The rates are set out in the licence document at award. Payments are made to the NSTA only by licence administrators (typically operators, who recoup the payments from the licensees in proportion to their interests in each licence) so the reconciled amounts reported in Table 4 in the Payments Data section do not reflect the extent to which payments to the NSTA are spread between licensees.

Onshore licensing was devolved to the Scottish Government on 9 February 2018 and to the Welsh Government on 1 October 2018. The power to set the consideration payable for a licence remains reserved by the UK Government as does the power to revoke licences. The NSTA has the responsibility for administering licences on behalf of the UK Government.  Scottish licence information for onshore licences, onshore fields and onshore wells is published on the Marine Scotland website. In Wales licences are not yet published online, however information at petroleum licences can be requested, free of charge, by post or email. All licences and appropriate associated documents will be published online during 2021.

Licence conditions and types of licences

Each licence contains detailed terms and conditions, but not all regulation is contained in the licence. The Petroleum Act 1998 requires these conditions — called model clauses — to be published first in secondary legislation except in particular cases [8].  In recent years, the model clauses have also been set out in full in the licence document.

Production licences are valid for a sequence of periods, or terms. These terms mirror the typical life cycle of a field: exploration, appraisal and production, and provide that each licence will expire automatically at the end of each term, unless the licensee has sufficiently progressed to warrant a move into the next term. The duration of each term depends on the type of the licence.

The NSTA publishes additional information about the different types of licences, their normal duration and different phases of the licensing lifecycle. 

While landward licences confer the right to search for, bore and extract petroleum on areas under licence, they do not exempt the licensee from other legal or regulatory requirements, including a need to obtain access rights from landowners or planning permission from relevant local authorities, or to conform to health and safety regulations.

In Northern Ireland, there is only one type of petroleum licence, this has broadly similar terms and conditions to onshore Petroleum Exploration and Development Licences (PEDLs) in Great Britain but also some differences. 

The MSG does not believe there are any non-trivial deviations in the award or transfer of licences for 2020 or previous years.

Licensing Review

The review into the future of offshore oil and gas licensing has concluded that a formal climate compatibility checkpoint building on current practice should be established. This will help ensure that any future licenses are only awarded on the basis that they are aligned with the government’s broad climate change ambitions, including the UK’s target of reaching net zero by 2050. A climate compatibility checkpoint will allow for an orderly transition, underpinned by ongoing production of oil and gas as long as we still require it domestically, while the sector increasingly bears down on its production emissions, and pivots to support the energy transition. The government has committed to designing the new checkpoint by the end of 2021

The oil and gas tax regime

As the UK’s oil and gas industry has developed over the last 40 years, successive governments have developed a tax regime designed to ensure that the nation receives a fair share of the profits from the exploitation of its oil and gas resources.

At the same time, the regime aims to support maximising the economic recovery of the UK’s remaining hydrocarbon resources. The fiscal regime which currently applies to oil and gas extractive activities comprised three separate taxes: Petroleum Revenue Tax (PRT), Ring Fence Corporation Tax (RFCT) and the Supplementary Charge (SC).

Additionally, from 26 May 2022, a new temporary Energy Profits Levy is charged on the profits of oil and gas extractive activities, increasing the headline rate of tax on these activities from 40% to 75% (the rate of EPL increased from 25% to 35% from 1 January 2023).

HMRC produce an Oil Taxation Manual  which provides an overview of the law and practice for the oil fiscal regime, in particular for Petroleum Revenue Tax, Ring Fence Corporation Tax, Supplementary Charge and Energy Profits Levy.

 

Petroleum Revenue Tax (PRT)

PRT is a tax on oil and gas production from the UK and UKCS. It is a field-based tax, which means that the profits from individual oil fields are calculated and subjected to tax separately. Companies do not aggregate their profits from different fields and cannot normally set off losses from one field against profits from another.

PRT was introduced by the Oil Taxation Act 1975 and was dis-applied in Finance Act 1993 for all fields given development consent on or after 16 March 1993. This means that fields that were given development consent after this date are not subject to PRT. The Chancellor announced at Budget 2016, that from 1 January 2016 the PRT rate would be permanently reduced to zero. However, it is important to note that PRT has not been abolished. Companies will still have to record and declare their profits and may be able to claim tax refunds for previously paid PRT where they make net losses after this date.

Despite the fact that PRT has been zero rated, it is possible that some companies may still make payments of PRT, for example where a payment is made to settle a previous year’s liability, or there is an adjustment to the amount of tax due from previous years.

Advance PRT Payments

Advance Petroleum Revenue Tax (APRT) was a temporary tax payable for periods from 1 January 1983 to 31 December 1986. The change was in effect a means of accelerating PRT payments.

Although APRT is no longer chargeable, repayments may arise due to the carry back of losses to periods in which APRT paid was set against a PRT liability. For practical purposes APRT repayments are included within the PRT figures in EITI reconciliation reports.

Ring Fence Corporation Tax (RFCT)

RFCT is a tax charged on the profits a company earns from carrying out oil and gas extraction activities in the UK and UKCS. This can include exploration, development and production activities. The profits chargeable to RFCT are calculated in the same way as for mainstream CT, but with some different rules relating to certain allowances, interest and transfer pricing. RFCT is charged at the company level, unlike PRT which was charged at the field level. This means that where a company has several different oil fields, it aggregates the profits from all those fields, and where any of the fields makes a loss, that loss can be set against profits from another field. The total profit across all fields in which a company operates is then charged to RFCT.

The ring fence separates the upstream UK oil and gas related activities of a company from any other activities of the company. It was introduced in the Oil Taxation Act 1975, and it means that if a company also carries on other activities which are not related to oil and gas extraction (this could include downstream oil and gas activity such as oil refining, or other completely separate activities), it will pay mainstream corporation tax (CT) on the profits of those other activities. Profits in the ring fence are taxed at 30%. This is significantly higher than the main rate of CT. If a company makes a loss on non-ring fence activities, it cannot set that loss against its ring fence profits (ring fence losses can be set against non-ring fence profits).

If a company makes a small profit (less than £300,000) on its ring fence activities, it pays tax at the small profits rate of 19% on those profits. If its profits are between £300,000 and £1,500,000 it can claim Marginal Relief, to remove the cliff-edge between 19% and 30% as soon as its profits are above £300,000.

Supplementary Charge (SC)

SC is an additional tax on a company’s adjusted ring fence profits. It was introduced in 2002. Like RFCT it is charged at the company level. The starting point for calculating the SC is the company’s profits subject to RFCT. These profits are then adjusted to remove any finance costs, which are not allowed as a deduction for SC purposes. The company may, however, be able to reduce its profits subject to the SC by virtue of certain allowances: the Investment Allowance and Cluster Area Allowance, and the Onshore Allowance, which are outlined below. The company’s adjusted ring fence profits are then charged to SC at a rate of 10%.

Summary of rates 

  • PRT – 0%
  • RFCT – 30%
  • SC – 10%

Interaction

PRT is an allowable deduction in calculating profits subject to RFCT and SC. Equally, any refund of PRT is a taxable receipt for RFCT and SC purposes. RFCT and SC are charged on the same profit base, so neither is allowable as a deduction in calculating the profits chargeable to the other.

This means that the overall marginal tax rate in 2019 was 40%. An example of this is shown below:

Table 6. Illustrative tax calculation
TaxPRT or non-PRT liable field
Profit£1,000
PRT at 0%£0
Profits after PRT£1,000
RFCT at 30%£300
SC at 10%£100
Total tax (PRT+RFCT+SC)(£400)
Profit after tax£600
Tax as a % of pre-tax profit40%

There have been numerous changes to the tax rates for PRT, RFCT and SC. PRT peaked at 75%, was reduced to 50% by Finance Act 1993, and as noted above, was permanently zero-rated at Budget 2016. Mainstream CT rates have been reduced substantially since 2008, but the RFCT rate has remained at 30%, creating a differential between the two. SC has varied between 10% and 32% since its introduction.

Previously, there was also a royalty levied at 12.5% of the value of petroleum which was generally measured as “well head value”. This was abolished for new fields in phases starting in 1983 with abolition in its entirety with effect from the end of 2002 as it distorted investment incentives. In addition, a Supplementary Petroleum Duty (SPD) was in place in 1981 and 1982.

Allowances

There are various allowances that apply to reduce the amount of PRT, RFCT or SC that a company has to pay.

PRT allowances

A number of allowances used to be available under the PRT regime to prevent an excessive PRT burden falling on smaller, more economically marginal fields. Oil Allowance was the only one that was still relevant to years immediately prior to 2016. Oil Allowance ensures that many small fields are effectively free from PRT. The available amounts are converted each chargeable period into a “cash equivalent” which then reduces the liability to PRT.

RFCT allowances

Capital allowances

Capital allowances are a feature of business taxation in the UK and apply to the mainstream CT regime (as well as to income tax). For CT purposes, the general rule is that capital expenditure is not allowed as a deduction for tax purposes. This means that profits chargeable to CT cannot be reduced by depreciation or similar expenses. The capital allowance regime exists to provide some relief for capital expenditure incurred.

There are specific rules and rates of allowances available for companies carrying on a ring fence trade. These allowances mean that in practice, virtually all capital expenditure incurred by oil and gas companies for the purposes of their ring fence trades will qualify.

There are three types of allowance which are commonly relevant for companies carrying on a ring fence trade. Research and Development Allowance (RDA), Mineral Extraction Allowance (MEA) and Plant and Machinery Allowances (PMA). RDA and MEA are primarily relevant to companies incurring capital expenditure on exploring for, appraising and gaining access to oil and gas during the pre-production phase. PMAs are available on capital expenditure on items of plant or machinery used in the ring fence trade. Mostly these are 100% First Year Allowances (FYAs), which allow the full amount of the expenditure to be written off for tax purposes in the accounting period in which the expenditure is incurred [9]. 

Ring Fence Expenditure Supplement (RFES)

RFES is designed to assist companies that do not yet have sufficient RFCT profits against which to set their exploration, appraisal and development costs. The RFES currently increases the value of unused expenditure carried forward from one accounting period to the next by a compound 10% a year for a maximum of 10 years (6 years prior to 2014). The company can elect which periods it wants to claim RFES for. They do not have to be consecutive years. The Oil Taxation Manual provides further guidance on Ring Fence Expenditure Supplement.

Research and Development Expenditure Credit (RDEC)

RDEC is a tax credit available to companies operating in all sectors. It is generated by spend on research and development, and is claimed as a tax credit. There are a number of ways in which a company can receive payment of their RDEC claim, including offsetting against another of its tax liabilities and receiving a cash repayment.

More information on RDEC can be found in HMRC guidance and statistics on RDEC can be found here.

For EITI reporting purposes, tax payments/repayments are reported exclusive of any adjustment for RDEC. 

SC allowances

Cluster Area Allowance

Legislation in the Finance Act 2015 introduced a new Cluster Area Allowance, which aims to support large development projects in areas of high pressure and high temperature, encouraging exploration and appraisal in the surrounding area (or “cluster”). The allowance is generated by incurring capital expenditure, and certain types of operating and leasing expenditure within the cluster area. The value of the allowance is 62.5% of the qualifying expenditure incurred. Any allowance generated is carried forward year on year until it is activated. Allowance is activated by production income from the cluster area. Once the allowance has been activated it is set against profits subject to the SC, so that any such profits are only subject to RFCT at 30%. Cluster areas are determined as such by the OGA, and the only area determined to date is the Culzean Cluster Area in the Central North Sea.

Onshore Allowance

The Onshore Allowance was introduced in Finance Act 2014 to provide support for the early development of onshore oil and gas projects which were economic but not commercially viable at the prevailing tax rates. The onshore allowance covers both conventional and unconventional hydrocarbons and replaces all existing field allowances for onshore projects. The allowance works in a similar way to Cluster Area Allowance: it is generated by capital expenditure, in an amount equal to 75% of that capital expenditure. Once the allowance is activated by production income in relation to an onshore site, the allowance is used to reduce the adjusted ring fence profits which are subject to SC.

Investment Allowance

The existing system of offshore field allowances was replaced by a single Investment Allowance in Finance Act 2015. Similarly to the Cluster Area and Onshore Allowances, the Investment Allowance is generated by capital expenditure, and certain types of operating and leasing expenditure incurred in relation to a qualifying oil field. The amount of allowance generated is equal to 62.5% of qualifying expenditure. Investment Allowance is activated by production income from the field, unlike Cluster Area Allowances, which can be activated by income from any field in a designated cluster. Once activated, it is used to reduce the adjusted ring fence profits chargeable to the SC.

Losses

When a business makes a loss, it may be able to get relief for that loss through the tax system. Loss relief is not unique to the oil and gas regime: it is a feature of income tax, mainstream CT and other regimes too. Broadly, loss relief works by allowing a loss made in one period to be set off, in certain circumstances, against profits in the same or other periods.

PRT

PRT is a field-based tax, so loss relief is normally available only against profits from the same field. A loss can be carried back and set against profits of the field in previous periods, most recent period first, or carried forward to set against future profits, earliest period first. The loss is set against the profit before Oil Allowance. Only once, following cessation of production, all carry back and carry forward options are exhausted for that participator and there are no further profits against which the loss can be set, can the loss then be relieved against profits of earlier participators in the field. If there are still any unrelieved losses, they can be relieved against profits from another field.

Where a field has made an assessable profit, and paid tax in one period, and then has subsequently made a loss and the participator has chosen to carry the loss back, it could generate a repayment of tax.

RFCT

Where a company makes a loss for RFCT purposes, it can also choose how to treat that loss. The default position is that the loss is carried forward to set against future profits of the ring fence trade. However, the loss can also be set off against other (non-ring fence) profits arising in the year, or it can be carried back to set against the profits earned in previous years. Alternatively, where a company is part of a corporate group, it can surrender the loss to another company making a profit in the same period.

Under the normal rules, losses can be carried back only against profits arising in the previous year. However, these time limits are extended where the trade has ceased, in which case the loss may be carried back up to three years. For ring fence trades, this time limit may be extended further where the loss is incurred as a result of decommissioning expenditure. In such situations, the loss may be carried back to any period ending on or after 17 April 2002, regardless of whether trade has ceased.

SC

SC is calculated on the same basis as RFCT, but with adjustment for finance costs resulting in ‘adjusted ring fence profits’. However, there is no loss relief for SC per se. Rather, if a company makes a RFCT loss, and elects to carry it forward or backward, it will reduce the RFCT profits, and therefore the adjusted ring fence profit subject to SC of the subsequent or previous period will also be reduced, potentially to nil, generating a repayment of SC where SC has already been paid.

Variations in tax payments and repayments

The amount of tax paid by a company can vary year on year for a number of reasons. Perhaps most obviously, changes in tax rates will affect the amount of tax paid. In recent years, the rates of PRT and SC have both dropped, reducing the amount payable under these taxes. The level of profits (or losses) made by a company will also vary year on year. Factors such as capital expenditure incurred both on decommissioning and on exploration and investment can reduce profits, and variations in the oil price will have a substantial impact on trading receipts. Equally, as explained above, while a company may make a profit in a year, if it has a loss to set against that profit, the amount of tax payable may fall, or indeed lead to a repayment of tax.

Companies are charged PRT for chargeable periods of 6 months, running from 1 January to 30 June, and 1 July to 31 December. Companies’ profits are charged to RFCT and SC for accounting periods (APs). APs normally last for one year, although they can sometimes be shorter. Different companies have different APs, although commonly calendar or financial years are used.

PRT Payments

PRT instalments are due based on the previous chargeable period. From 2016, as the PRT rate was reduced to nil, PRT payments were only made to true up previous year’s liabilities or instalments made prior to the announcement of PRT being zero-rated at the 2016 Budget.

RFCT/ SC payments

The rules for payment of RFCT and SC differ from the payment rules for mainstream CT. Payments of RFCT and SC are made in three equal instalments: 6 months and 13 days from the start of the AP, 3 months from the first instalment due date , and 14 days from the end of the AP. These payments are in addition to non-ring fence CT payments which will remain payable under the quarterly instalment payments (QIPS) regime.

Decommissioning

Decommissioning is an inherent cost of doing business in the UKCS. As a result, tax relief is given for decommissioning costs but not until they are incurred and the decommissioning is carried out. For accounting purposes a company is required to make an annual provision. However, this cannot be deducted for tax purposes as the cash has yet to be spent, and the decommissioning has not actually happened.

If decommissioning expenditure produces an overall loss for a year then, as explained above, the loss may be carried back against previous ring fence profits of that company, as far as 2002 for RFCT and SC, and almost indefinitely against field profits for PRT. Losses generated by decommissioning costs and carried back to be offset against previous profits are relieved at the RFCT and SC rates to which those earlier periods were subject to. However, SC relief is subject to a further restriction [10].  

In most cases, the maximum rate of tax relief for PRT fields is 75%, but again is dependent on the prevailing tax rate in the period the losses are carried back to. The amount of relief available is limited to the taxable profits of the relevant field/company and in economic terms, represents a repayment of tax that has been overpaid through the profitable life of the company or field.

HMRC's latest estimate of the likely cost to the Exchequer, based on current estimates of decommissioning costs, is £21.8 billion [11].

Decommissioning Relief Deeds (DRDs)

In 2013, following extensive discussions with industry, the Government introduced legislation giving it the statutory authority to sign contracts (DRDs) with companies operating in the UKCS. The aim of the DRD is to provide certainty over the availability of decommissioning tax relief for the purposes of putting up security against the risk of default.

The DRD works by guaranteeing the tax relief due on decommissioning expenditure, based on the relief available at Finance Act 2013 (FA13). It allows a company to claim a payment from the Exchequer if, as a result of changes to the tax system, the relief available to the company on its decommissioning expenditure is less than that which would have been due under the rules as at FA13 (however, this does not apply if the relief is less due to changes in tax rates.)

The DRD will also pay out to a company that picks up the decommissioning liabilities of another company that has defaulted under its Petroleum Act 1988 obligations – for example if the company becomes insolvent – to ensure that the company incurring the default expenditure is able to get relief. This provides industry with certainty over the availability of decommissioning tax relief in future years and has unlocked additional investment capital in the UKCS by allowing companies to provide security for their decommissioning liabilities on a post-tax basis.

Each year the Treasury reports to Parliament the number of Deeds it has entered into that year, the total number of DRDs in force, the number and amounts of any payments made under the Deeds and an estimate of the maximum amount liable to be paid. 

Energy Profits Levy

With effect from 26 May 2022, the Energy (Oil and Gas) Profits Levy Act 2022 introduced a new, temporary 25% levy on companies producing oil and gas in the UK or on the UK Continental Shelf. The Autumn Statement 2022 announced several changes to the EPL that would take effect from 1 January 2023. These include increasing the rate of EPL to 35%, extending the end date of the EPL to 31 December 2028 and introducing a new 80% Decarbonisation Investment Allowance. The levy applies to a company’s ring fence profits computed for ring fence corporation tax purposes, but with a number of adjustments. It is charged as if it were an amount of corporation tax, and so the administration of the levy mirrors that for corporation tax.

In summary, the adjustments to profits are:

• financing and decommissioning costs are added back in

• repayments of PRT arising from decommissioning are left out of account

• an 29% allowance for investment expenditure is deductable

• an 80% allowance for decarbonisation expenditure is deductible

Loss relief is available within the levy regime, but there is no cross over to any other ring fence taxes. Levy losses can be relieved through i) carry back of 12 months against previous levy profits (3 years for terminal losses), ii) carried forward to set against future levy profits, and iii) group relief in year to another company in the group with levy profits.

On 9 June 2023, the government announced the EPL Energy Security Investment Mechanism (ESIM). It will mean that EPL will remain in place until March 2028 unless the average oil and gas prices, over a six-month period, are at or below the ESIM price thresholds (calculated using a 20-year historic average at the end of 2022), these are set at $71.70 per barrel for oil and £0.54 per therm of gas. If that happens, the tax rate for oil and gas companies will return to 40%, the rate before EPL was introduced.

At Autumn Statement 2023, the government published a technical note setting out the practical application and technical detail of the ESIM.

 

Looking ahead

The UK Government is committed to having an oil and gas tax regime that strikes the right balance between attracting investment and ensuring a fair return for the nation from the use of its resources.

The OGA Levy

The North Sea Transition Authority - formerly the Oil and Gas Authority (OGA) - is a Government-owned not-for-profit company largely funded by fees for specific activities and by a per-licence levy, known as the OGA Levy, on offshore licence holders apportioned between in-production (89%) and pre-production (11%) licence holders. The OGA Levy was introduced with effect from 1 October 2015. The NSTA reports on Levy income in its annual accounts.

Payments to The Crown Estate (TCE) and Crown Estate Scotland (CES)

Payments are made to The Crown Estate and Crown Estate Scotland by companies for the pipelines they operate in respect of extractive-related activities.

Installation of oil and gas infrastructure (including platforms, subsea facilities and pipelines) located within the 12 nautical mile territorial limit or, in the case of pipelines, crossing the foreshore, requires the agreement of The Crown Estate or Crown Estate Scotland, as appropriate. The Crown Estate and Crown Estate Scotland grant leases for pipelines on or buried beneath the seabed, within the 12 nautical mile territorial limit and crossing the foreshore that they control, which transport oil and gas from offshore reservoirs to processing terminals on the UK coastline. A list of TCE offshore and onshore pipeline agreements is available here.

Current Crown Estate Scotland terms and conditions for pipelines are published on the CES website. These terms and conditions have recently been the subject of a periodic review, which is in the process of being finalised. Once updated terms and conditions are available, they will be published. Crown Estate terms and conditions are opaque.

There are no other Crown Estate or Crown Estate Scotland licences or contracts granted related to oil and gas extraction.

Notes and References
  1. Wytch Farm in Dorset, England, is the only substantial onshore field and is partly covered by a “seaward” licence; the drilling sites are onshore, but some of the wells extend under Poole Harbour. Wytch Farm is here treated as offshore.
  2. Net natural gas production equals gross production less producers’ own use, that is the gas used in the course of production of oil and gas and therefore not available for sale to end users. The OGA publishes data relating to production of UK oil and gas, including production data for individual fields, production and expenditure projections and tables and charts on UKCS income and expenditure.
  3. Statistical Review of World Energy
  4. This sub-section draws on the material on Licensing and consents on the OGA’s website to which reference may be made for further details. 
  5. OGA documentation of award rounds
  6. See for example the announcement of the 14th landward licensing round including the assessment criteria
  7. For further details see the OGA Licence Assignments and details of current licences.
  8. Petroleum Licensing (Exploration and Production) (Landward Areas) Regulations 2014
  9. Oil and gas: further information on these capital allowances: HMRC - Oil taxation manual: Capital allowances and Oil taxation manual: Corporation tax ring fence: first-year allowances for a ring fence trade
  10. For more information on the SC restriction please see the HMRC Oil taxation manual: the supplementary charge
  11. See Estimates of the Remaining Exchequer Cost of Decommissioning UK Upstream Oil and Gas Infrastructuredocument on the NSTA website
Glossary of Abbreviations
AbbreviationExplanation
APAccounting Period
APRTAdvance Petroleum Revenue Tax
BEISDepartment for Business, Energy and Industrial Strategy
BGSBritish Geological Survey
boeBarrel(s) of oil equivalent
Brentas applied to trading, the standard quality of oil in Europe and elsewhere comprising a blend of four North Sea crudes from the Brent, Ekofisk, Forties and Oseberg fields
CESCrown Estate Scotland
CNSCentral North Sea
CTCorporation Tax
DECCDepartment of Energy & Climate Change (now part of BEIS)
DfEDepartment for the Economy
DRDDecommissioning Relief Deed
DUKESDigest of UK Energy Statistics
EITIExtractive Industries Transparency Initiative
EUEuropean Union
FAFinance Act
FYAsFirst Year Allowances
HMRCHer Majesty’s Revenue and Customs
LNGLiquefied Natural Gas 
MEAMineral Extraction Allowance
NBPNational Balancing Point
NGLsNatural Gas Liquids
NSTANorth Sea Transition Authority
OBROffice for Budget Responsibility
OGAOil and Gas Authority
ONSOffice of National Statistics
PEDLPetroleum Exploration and Development Licence
PMAPlant and Machinery Allowances
PRTPetroleum Revenue Tax
QIPQuarterly Instalment Payment
RDAResearch and Development Allowance
RFCTRing Fence Corporation Tax
RFESRing Fence Expenditure Supplement